Project Description
Replacement of a structurally deficient steel beam bridge. Minimal roadway improvements including shoulder re-grading.
Project Location and Limits:
Centerburg Road about 1/4 mile west of Condit Road.
Road Closure Information
Centerburg Road closed to through traffic between Porter Central Road and Condit Road with posted detour. Approximate 2-month closure.
Project Schedule
Design engineering: 2009-10
Right-of-way acquisition: 2010-11
Utility relocation: 2011
Construction: 2012
Engineering Information
Construction documents prepared by E.P. Ferris & Associates.
Construction Information
Contract to be advertised for bids.
Estimated Project Cost
$400,000