Project Information:
Planned improvements to the intersection of South Old State and Hollenback Road will include:
- A traffic signal and turn lanes on each approach of South Old State and Hollenback Road.
- Widening South Old State to 3 lanes from Avonlea Way/Hidden Cove to north of Hollenback Road.
- Widen Hollenback Road to 3 lanes from South Old State Road west about ½ mile.
Schedule:
Design: 2022-25
Right of way purchase: 2026
Utility relocation: 2026-27
Construction: Late 2026 to late 2027
Maintaining Traffic During Construction:
Construction will take about 10 months from start to finish. Northbound traffic on South Old State will be maintained for the duration of the project. Southbound traffic will be detoured for up to 5 months to allow for road widening (half of the road done at a time). Hollenback Road will close west of Old State for about 3-4 months and east of Old State for about 1-2 months.