Project Description

Resurfacing and preventive pavement maintenance on 90 miles of county and township roads.

 

Construction Updates

07-16-2012: Old State Road Resurfacing Begins This Week:

Resurfacing of Old State Road from Orange Road to U.S. 36 will begin July 16. One lane of traffic will be maintained at all times. Road work will be limited to off-peak hours in the areas south of Cheshire Road. The resurfacing will take about 2 weeks to complete.

The resurfacing will include chip sealing of the existing pavement to seal cracks prior to the asphalt overlay. Please drive slowly in areas with freshly placed gravel. We appreciate your patience during this work!

 

06-08-12: 2012 Road Improvement Program to Begin June 11:

Work will begin the week of June 11 on resurfacing various county and township roads in Delaware County. The first phase of work will include pavement repairs and chip sealing on various roads. More information will be posted as construction progresses on this project.

 

Current Two-Week Construction Schedule

 


Road Closure Information

Traffic to be maintained in the work zones using flaggers and a minimum of 1-lane, 2-way operation. Brief closures may also be required.

 


Project Schedule

Design engineering: Fall 2011 to spring 2012

Right-of-way acquisition: None

Utility relocation: None

Construction: June to September 2012

 


Engineering Information

Construction documents prepared by the Delaware County Engineer’s Design Department.

 


Construction Information

The awarded contractor is The Shelly Company, Thornville, Ohio.

 


Estimated Project Cost

Awarded contract amounts:

  • County portion: $2.8 million