Project Description

Replacement of a narrow, steel jack arch bridge in poor structural condition. Project includes removal of existing bridge, and installing a 28 x 10 precast, reinforced concrete arch culvert. Approach improvements including pavement and shoulder widening, drainage improvements, and guardrail installation complete the project.

 

Project Location and Limits:
Hartford Road about ¼ mile east of Ross Road. Total project length is about 400 feet.

 


Road Closure Information

Road closed to through traffic with detour posted. Local resident traffic maintained.

 


Project Schedule

Design engineering: November 2003 to February 2004

Right-of-way acquisition: April to July 2005

Utility relocation: June 2005 to January 2006

Construction: April to June 2006

 


Engineering Information

Construction documents prepared by the Delaware County Engineer’s Design Department.

 


Construction Information

Built by Delaware County Highway Department.

 


Estimated Project Cost