Project Description

Replacement of a narrow steel beam bridge in poor structural condition. Project includes removal of existing bridge, and installing a 14 x 7 precast reinforced concrete box culvert. Approach improvements including pavement and shoulder widening, drainage improvements, and guardrail installation.

Project Location and Limits:

Justamere Road about 1/4 mile east of Lane Road. Total project length is about 400 feet.

 


Road Closure Information

Road closed to through traffic with detour posted. Local resident traffic maintained.

 


Project Schedule

Design engineering: August 2005 to December 2006

Right-of-way acquisition: February to April 2007

Utility relocation: March to April 2007

Construction: March to June 2007

 


Engineering Information

Construction documents prepared by the Delaware County Engineer’s Design Department.

 


Construction Information

Project constructed by Delaware County Highway Department. Precast concrete box culvert by United Precast, Inc. of Mount Vernon, Ohio. Guardrail by Paul Peterson Company of Columbus, Ohio.