Project Description
Replacement of the Stockwell Road bridge over Big Walnut Creek including major approach roadway construction. New bridge is a 94 foot span prestressed concrete I-beam superstructure on reinforced concrete abutments with drilled shaft foundations. The improvement also includes major approach reconstruction and realignment for improved safety and drainage.
Project Location and Limits:
Patrick Road from Creek Road about 1/2 mile west on Patrick Road.
Road Closure Information
Road closed to through traffic with detour posted.
Project Schedule
Design engineering: December 2002 to August 2003
Right-of-way acquisition: 2004-2005
Utility relocation: 2004-2005
Construction: March to August 2006
Engineering Information
Construction documents prepared by WD Partners, Inc. of Columbus, Ohio.
Construction Information
Contractor: Eagle Bridge Company, Inc., Sidney, Ohio.
- Contract amount $844,885.49
Estimated Project Cost
$1.0 million