Construction Updates
June 17, 2019 – Lewis Center and North Road Intersection to Close for 60 Days Beginning June 24
The intersection of Lewis Center and North Road will close beginning on or about June 24 to begin construction of a new single-lane modern roundabout. This is the second phase of a $3.8 million project to improve both Lewis Center and North Roads in this area. During the closure, the posted detour route will use Shanahan Road, US 23, Orange Road and Old State Road.
Phase 1 of the project which includes reconstruction of North Road will be wrapping up over the next week with paving on North Road as weather permits. Local traffic to residences in the work zone should enter/exit from Shanahan Road during the intersection closure.
Phase 3 will begin in August with a 6 week closure of Lewis Center Road between the Olentangy HS Entrance and Weeping Rock Creek for replacement of a large culvert. All road work will be wrapped up in October this year.
Project Description
Planned improvements to Lewis Center Road (CR 106) between the Olentangy High School entrance and the CSX/Norfolk-Southern Railroad, and North Road between Lewis Center Road and North Farms subdivision. The project will also include a single-lane modern roundabout at the intersection of Lewis Center and North Road. Grading and drainage improvements will be included to make way for a future shared use path to be built on the north side of Lewis Center Road and west side of North Road as a separate project.
Updates
Public Information Meeting Scheduled for October 17, 2017:
The Delaware County Engineer’s Office will be hosting an informational meeting regarding planned improvements to Lewis Center Road and North Road in Lewis Center.
Tuesday, October 17, 2017 4:30 p.m. to 6:30 p.m.
Lewis Center United Methodist Church (Fellowship Hall)
1081 Lewis Center Road
Lewis Center, OH 43035
The meeting will be an open house format. There will be no formal presentation; you are free to come and go as your schedule allows. Representatives from the County Engineer’s Office and the design consultant will be available to answer your questions about the project.
If you are unable to attend the meeting the information provided will also be available on the Delaware County Engineer’s website.
So that we can incorporate any necessary changes into the proposed plans, please provide any comments you have about the project no later than November 17, 2017.
If you need special assistance or wish to provide your comments by phone or email, please contact Robert Riley, Chief Deputy Engineer at (740) 833-2400 or at rriley@co.delaware.oh.us.
Exhibits Provided at the Meeting
- Lewis Center and North Road Project Plan (993KB)
- Detail of Lewis Center Road (318 KB)
- Detail of North Road (315 KB)
- Typical Roadway Sections (330 KB)
- Project Information Sheet (620 KB)
Construction and Road Closure Information
Phase 1 construction will include closure of North Road, while traffic on Lewis Center Road is maintained.
Phase 2 construction will include construction of the new roundabout at the intersection of Lewis Center and North Road.
Phase 3 construction will include construction on Lewis Center Road between the Olentangy High School entrance and the Lewis Center United Methodist Church.
Dates will be provided when available.
Project Schedule
Design engineering: January 2016 to December 2017
Right-of-way acquisition: October 2017 to April 2018
Utility relocation: March 2018 to July 2018
Construction: Fall 2018 to Summer 2019
Engineering Information
Construction plans prepared by the IBI Group, Columbus, Ohio.
Estimated Project Cost
$3.8 million. All costs to be paid by Delaware County and Orange Township.