Construction Updates

Construction is scheduled to begin in early June 2019 with a closure of Freeman Road for approximately 7 weeks to reconstruct and realign the Freeman Road approach to the intersection.  More details will be provided when exact dates are available.


Project Description

Construction of a new traffic signal and realignment of Freeman Road at Worthington Road.


Road Closure Information

Freeman Road will be closed for about 60 days with a posted detour to be rebuilt and realigned at Worthington Road.  Two-way traffic on Worthington Road and Olympic Way will be maintained.


Project Schedule

Design engineering: 2015-16

Right-of-way acquisition: 2018

Utility relocation: Fall 2018 to Spring 2019

Construction: June to September 2019


Engineering Information

Construction documents prepared by Patrick Engineering of Columbus, Ohio.


Construction Information

Prime contractor is Shelly & Sands, Inc.


Estimated Project Cost

$800,000