Project Description (Phase 2)

Reconstruction and widening of Orange Road to 5 lanes from 500 feet east of Orange Centre Drive to Green Meadows Drive, including new traffic signals at North Central Drive, Highfield Drive, Green Meadows Drive and Blue Holly Drive.

Phase 2 project exhibit

 

Project Phase 1 was constructed in 2016-17 and included reconstruction and widening of Orange Road from U.S. 23 to about 500 feet east of Orange Centre Drive.  Click here for information about Phase 1


Schedule

Phase 2:  Orange Centre Drive to Green Meadows Drive:

  • Design engineering:  2016-18
  • Right of way acquisition: 2019
  • Utility relocation: 2019-20
  • Construction: 2020-21

Engineering Information

Preliminary engineering by CHA of Columbus, Ohio.


Estimated Project Cost

Phase 2: $3.5 million