The Glick Road (Concord and Liberty Township) West-bound Lane, over the O’Shaughnessy Dam, will be CLOSED from 9:00 AM to 4:00 PM on Monday (4/15) thru Monday (7/22).

This is a City of Columbus Project that involves masonry and lighting repairs at the power gatehouse, outlet gatehouse and pavilion, while also replacing broken guardrail balusters along sidewalk at various points along the bridge.

  • The westbound lane of Glick Road will close between Riverside Drive (SR 257) and Dublin Road from April 15-July 22, 2024. The westbound lane will be closed between 9:00 a.m.to 4:00 p.m. Monday – Friday..
  • Eastbound Glick Road will remain open throughout the project.
  • To allow for traffic for The Memorial Tournament, Glick Road will be fully open June 3rd to 9th.
  • This is a City of Columbus-led project and any/all questions should be directed to them.