The contractor for Norfolk Southern Railroad will be repairing railroad crossings from 9/14 thru 9/25. During construction, the railroad crossing will be Closed to all Traffic.

Each crossing is expected to be closed for approximately 1–2 days, and the work is weather dependent.

Work Schedule:

The contractor will address the crossings in the order listed below, moving from south to north. Work will begin at the E. Orange Road Crossing on September 14th.

Orange Township

  • E. Orange Road — First closure begins September 14th to September 16th.
    [Permit] | [Detour]
  • Shanahan Road — Orange Township / Berlin Township – Tentative Closure September 15th to September 17th.
    [Permit] | [Detour]

Berlin Township

  • Cheshire Road – Tentative Closure September 16th to September 18th.
    [Permit] | [Detour]
  • Berlin Station Road – Tentative Closure September 21st to September 23rd.
    [Permit] | [Detour]

Troy Township

  • Penry Road – Tentative Closure September 23rd to September 25th.
    [Permit] | [Detour]
  • Troutman Road – Tentative Closure September 23rd to September 25th.
    [Permit] | [Detour]

Important Information:

  • No traffic will be permitted to cross the railroad tracks while work is underway.
  • Each crossing closure is expected to last approximately 1 to 2 days.
  • All work is weather dependent, so the dates may change.