08/05/2025 UPDATE: The first phase of asphalt milling took longer than anticipated. The second phase of milling that includes the first layer of asphalt will begin today (Tuesday 08/05) and finish tomorrow (Wednesday 08/06).
Final layer of asphalt will be placed later this week and traffic will be maintained by using flaggers. Today (08/05) and tomorrow (08/06) are the days when the full closure will impact area residents and the access to homes on Highmeadows Village Drive.
07/31/2025 Update: Due to current weather conditions, the road work on Highmeadows Village Drive will begin on Friday (08/01) with flaggers and no road closure. Highmeadows Village Drive will now be CLOSED on Monday (08/4).
Highmeadows Village Drive (Orange Township) will Be CLOSED on Thursday (July 31st) and Friday (August 1st) for a Road Resurfacing Project.
All traffic will be maintained to all residents that live on Highmeadows Village Drive throughout this project. There may be times when the contractor is working in front of driveways and access could be blocked for up to 30 minutes. We advise that people give themselves a little extra time when needing to leave their homes.
All access to side streets will also be maintained and flaggers will be on site to direct traffic around the construction. The road work will run from Slate Run Drive to River Bend Ave.
The two-day closure is for the full depth milling and first layer of asphalt. After that work is completed the contractor will still have final paving to complete which they will do without a full closure.
This Roadwork is always Weather Dependent.