6/12 UPDATE:

  • The Orange Road Crossing is being Paved today (6/12) and will OPEN for traffic tomorrow (Saturday 06/13) morning.
  • They will start CLOSING the following Crossing on Monday (06/15) at 7:00 AM:
        • Lewis Center Road
        • Shanahan Road
        • Berlin Station Road
  • They plan on working every day from Monday (6/15) thru Monday (6/22).
  • They are POSTPONING the CLOSURES at the Peachblow Road Crossing and the Cheshire Road Crossing.

This schedule and the sequence of Crossing Closures (below) can change at any time and with little-to-no notice.

 

________END UPDATE ____________________

 

6/10 UPDATE:

  • They will be Closing the Orange Road Crossing tomorrow (Thursday 6/11) morning (7:30) for Repairs.
  • Paving the Orange Road Crossing will occur on Friday (6/12) and the Crossing will open for traffic later that day.
  • They will Close the Lewis Center Road Crossing on Monday (06/15) at 7:00 AM.
  • They plan on working every day from Monday (6/15) thru Monday (6/22).
  • During this timeline, there may be multiple Crossing Closures and there maybe Crossings Closed over the 6/19 (Holiday) thru 6/21 weekend (we asked them to avoid it if at all possible).
  • They are postponing the Peachblow Road Crossing Closure.

This schedule and the sequence of Crossing Closures (below) can change at any time and with little-to-no notice.

 

_____ END UPDATE _____

 

The new Start Date has been Changed to Thursday (6/11) at 7:00 AM – and the Crossing at Peachblow Road has been removed.

The Contractor for the CSX Railroad will be working in our County to upgrade railroad crossings. No traffic will be able to cross the railroad tracks while the work is being performed. The length of the Crossing Closures at each site will be approximately 2-5 days (or less). The Work Schedule will be Monday thru Thursday with a start time of 7:00 AM.

** Please note that there may be multiple Crossing Closures at the same time.

The Delaware County Railroad Crossings listed below are in the order that they will be addressed by the Contractor as they move from South to North with the first Crossing Closure at the E. Orange Road – and upon completion, moving to the next Crossing on the list.

Orange Township:

  • E. Orange Road
  • Lewis Center Road
  • Private Crossing
  • Shanahan Road (Orange & Berlin Townships)

Berlin Township:

  • Private Crossing
  • Peachblow Road – Postponed
  • Cheshire Road – Postponed
  • Private Crossing (House)
  • Berlin Station Road
  • Private Crossing
  • Curve Road

Brown Township:

  • Harris Road
  • County Home Road

Oxford Township

  • Shoemaker Road
  • Private Crossing (House)
  • Steamtown Road

Please Contact Geoff Reeder at Safety Services & Supply (419-453-3166) with any questions or concerns.