Project Schedule
Design engineering: 2006 to 2009
Right-of-way acquisition:
- Phase 1: Spring to Fall 2008
- Phase 2: Summer to Fall 2009
Construction:
- Phase 1: December 2008 to August 2009;
- Phase 2: Fall 2009 to Spring 2010
Engineering Information
Engineering by WD Partners of Columbus, Ohio.
Construction Information
Phase 1 (bridge) construction contract awarded to Eagle Bridge Company of Sidney, Ohio for $2,717,707.75
Phase 2 (roundabout) estimated cost $695,000.