Project Description

Replacement of the Stockwell Road bridge over Big Walnut Creek including major approach roadway construction. New bridge is a 94 foot span prestressed concrete I-beam superstructure on reinforced concrete abutments with drilled shaft foundations. The improvement also includes major approach reconstruction and realignment for improved safety and drainage.

 

Project Location and Limits:
Patrick Road from Creek Road about 1/2 mile west on Patrick Road.

 


Road Closure Information

Road closed to through traffic with detour posted.

 


Project Schedule

Design engineering: December 2002 to August 2003

Right-of-way acquisition: 2004-2005

Utility relocation: 2004-2005

Construction: March to August 2006

 


Engineering Information

Construction documents prepared by WD Partners, Inc. of Columbus, Ohio.

 


Construction Information

Contractor: Eagle Bridge Company, Inc., Sidney, Ohio.

  • Contract amount $844,885.49

 


Estimated Project Cost

$1.0 million