The contractor for Norfolk Southern Railroad will be repairing railroad crossings from 9/14 thru 9/25. During construction, the railroad crossing will be Closed to all Traffic.
Each crossing is expected to be closed for approximately 1–2 days, and the work is weather dependent.
Work Schedule:
The contractor will address the crossings in the order listed below, moving from south to north. Work will begin at the E. Orange Road Crossing on September 14th.
Orange Township
- E. Orange Road — First closure begins September 14th to September 16th.
[Permit] | [Detour] - Shanahan Road — Orange Township / Berlin Township – Tentative Closure September 15th to September 17th.
[Permit] | [Detour]
Berlin Township
- Cheshire Road – Tentative Closure September 16th to September 18th.
[Permit] | [Detour] - Berlin Station Road – Tentative Closure September 21st to September 23rd.
[Permit] | [Detour]
Troy Township
- Penry Road – Tentative Closure September 23rd to September 25th.
[Permit] | [Detour] - Troutman Road – Tentative Closure September 23rd to September 25th.
[Permit] | [Detour]
Important Information:
- No traffic will be permitted to cross the railroad tracks while work is underway.
- Each crossing closure is expected to last approximately 1 to 2 days.